Noble Helium told the Australian Securities Exchange on 25 November 2026 that its drilling rig and mast had cleared customs at the Kenya–Tanzania border and were on their way to Kinambo-1. The company expected to start drilling before the end of November, almost five months after its initial target of early July. The rig still needed to be assembled and commissioned at the site.
Kinambo-1 is now the only well Noble has committed to drill on the western margin of its wholly owned North Rukwa project in south-west Tanzania. Its results will guide the decision on a second well. The company enters the campaign with limited funding: at the end of September, it reported enough cash to cover 1.61 quarters of spending at the September quarter’s rate, when mobilisation had been paused to conserve cash.
What Kinambo-1 can establish
In May, Noble planned to drill two wells, one to about 430 metres and another to about 1,500 metres. On 13 November, it switched to a single 1,850-metre well, with a second to be drilled “only if required,” depending on the first well’s results. Noble said the change would avoid moving the rig between sites and allow its logging contractor, SLB, to collect measurements over the full depth of the well for an independent resource assessment.
The distinction between finding helium and showing it can be produced matters at North Rukwa. In 2023, the Mbelele wells recovered formation fluids from depths of 213 to 453 metres. Gas released from those fluids contained 0.4% to 2.46% helium, with the balance mostly nitrogen. The samples showed helium was present but did not establish how quickly gas could flow from a well.
At Kinambo-1, Noble plans to collect downhole measurements and samples for analysis on site and verification in a laboratory. It is targeting independent certification of reserves and resources in the first half of 2027. The company said it may prepare the well for future production testing, depending on the results. A measured flow rate is therefore not assured when drilling ends.
Funding the work before revenue
Noble reported A$3.9 million in cash, A$1.2 million in drawn loans and no undrawn credit facilities at the end of September. Outgoings were A$2.4 million for the quarter despite the pause in mobilisation. Its estimate of 1.61 quarters of funding was based on that spending rate, not on the cost of running the rig, paying a drilling crew and logging the well. Its auditor flagged material uncertainty over the company’s ability to continue as a going concern.
Noble also disputes a A$4.0 million claim from P R Marriott Drilling related to the 2023 campaign and the removal of that rig from Tanzania. Noble is defending the claim and has counterclaimed for delays. It argues that the net balance is A$655,141 in its favour; that is the company’s position, not a settled amount.
The company raised A$12 million in April at A$0.029 a share, a 40.8% discount to the previous close. Its share count rose from 599.5 million in April to 1.32 billion by 30 September. On 24 November, the shares closed at A$0.025, below the April issue price, giving Noble a market value of about A$31 million.
What the resource estimate is worth
Independent assessor NSAI put the best estimate of North Rukwa’s prospective helium resource at 118 billion cubic feet. That is an estimate, not a reserve proven to be commercially recoverable. Adjusting Noble’s November market value for its September cash and drawn debt gives an enterprise value of about A$28 million, or roughly US$18 million at the exchange rate used in its investor presentation. Dividing that by the prospective volume gives about US$0.16 per thousand cubic feet. It is a valuation ratio for an explorer, not a price for saleable gas.
Noble’s April presentation assumed a long-term bulk helium price of US$450 per thousand cubic feet. For comparison, the US Geological Survey put the 2025 US base price for Grade-A helium at about US$330 per thousand cubic feet before producer surcharges. Neither figure establishes what Noble could earn: it has no operating revenue, and a buyer, a sales price and the capital to build a plant are not secured by a resource estimate.
If drilling succeeds, Noble’s plan calls for a small western-margin operation generating cash flow within 18 to 24 months. That timetable depends on certification, an agreement to sell the gas and financing. Clearing customs moved the rig closer to the well site; the first drilling results will bear on the resource, while funding and commercial production remain separate questions.