Senate bill could raise data centers’ grid bills before new power lines arrive

The U.S. Senate voted 62–33 on Nov. 19, 2026, to pass a bill that would shorten federal reviews for energy projects and shift more transmission costs to large data centers. For landlords Equinix and Digital Realty, the two provisions would work on different schedules: higher charges could reach utility bills around 2028, while a new interstate power line could take more than a decade to plan and build.

Neither provision was law as of Nov. 27. The Senate amended and renamed H.R. 2347, a tax bill the House had already passed, so the House still needed to act on the Senate version of the Bipartisan American Affordability and Jobs Act. Speaker Mike Johnson said he would first seek approval under suspension of the rules, which requires a two-thirds vote of those present, then pursue a simple-majority route if necessary. An amendment that sponsors said would close a data-center loophole did not receive a vote after Sen. Jeff Merkley objected.

What the $55 billion estimate includes

Section 2107 would give the Federal Energy Regulatory Commission (FERC) 270 days after enactment to revise its transmission pricing policy for data centers with capacity above 20 megawatts. Utilities could charge wholesale customers seeking transmission service on those centers’ behalf for both the existing grid and the upgrades their demand triggers. The additional revenue would reduce transmission charges for the utility’s other customers.

Grid Strategies, a consultancy whose estimate was cited by Sen. Martin Heinrich, projected about $55 billion in data-center transmission charges over 10 years. That is the total, not the increase: about $35 billion would be additional to charges under current policy. The estimate assumes 40.3 gigawatts of new data-center capacity and excludes Texas because FERC does not traditionally regulate transmission service in the ERCOT market. It is not an official budget score, and the amount would depend partly on how much service falls under FERC’s wholesale pricing authority.

States set the retail tariffs that many data centers pay. A separate provision would let states require data centers to cover generation, storage and distribution costs as well. Grid Strategies estimated $136 billion in incremental generation costs over a decade if states adopted the provision. The consultancy described that figure as an indication of scale, not a precise forecast; some of those costs are already borne by data centers.

What an earlier opening is worth to Digital Realty

At Sept. 30, Digital Realty had 1,464 megawatts under construction, 63% of it leased. It expected the projects to cost $21.99 billion before adjusting for its ownership share, or about $15 million per megawatt. At the company’s expected stabilized cash yield of 11.6%, that works out to about $1.74 million in annual cash net operating income per megawatt.

For comparison, spreading Grid Strategies’ estimated additional transmission charges across the assumed capacity gives about $87,000 per megawatt per year, or 5% of that stabilized income. A month of operation at the stabilized rate would generate about $145,000 per megawatt—more than a year and a half of the estimated increase. That comparison illustrates the value of an earlier opening; it does not mean a newly opened facility would immediately earn its stabilized income or that the bill would advance a particular project.

The bill would set one- or two-year deadlines for federal environmental reviews and 150-day windows for many legal challenges. It would also let FERC permit certain interstate transmission lines if a state had not acted within a year. Shorter reviews could bring generation or grid connections forward, but they would not eliminate construction time. The Sierra Club’s Holly Bender noted that planning, approval and construction together can take more than 10 years for a line crossing state borders.

Who bears the utility bill

Digital Realty recorded $423.9 million in tenant utility reimbursements against $477.5 million in third-quarter utility expense. Tenants thus covered about 89 cents of each utility dollar that quarter. That does not guarantee the same recovery for a new transmission charge: vacant space, projects in development and leases that cap reimbursements leave some costs with the landlord. Timing also matters because Digital Realty still had $10.3 billion of its own share of spending left on projects under construction.

Equinix, which sells cabinet space and connections rather than primarily leasing large blocks of megawatts, already has an example of a different arrangement. In Hampton, Georgia, the company committed to fund all grid infrastructure costs for its data center over 20 years. That agreement shows how a developer can take responsibility for a project’s grid costs; it does not establish what Equinix would owe elsewhere.

Neither company’s 2026 payout figures assume that faster permitting will immediately deliver more rent. Equinix expected about $2.04 billion in cash dividends against $4.34 billion to $4.38 billion in adjusted funds from operations, a payout of roughly 47%. Digital Realty’s indicated annual dividend of $4.88 per share was about 59% of the midpoint of its $8.30 to $8.35 guidance for core funds from operations per share, excluding net promote. The companies use different measures, and neither ratio settles who would absorb a future charge. That depends first on what the House passes, then on federal pricing rules, state tariffs and lease terms.

Further reading