Nvidia shares rose 31.5% to $165.05 on Nov. 23, 2026, after its board reinstated Jensen Huang as chief executive. By Nov. 27, the stock had slipped to $150.49, according to Ainvest data. The leadership reversal changed neither the price Nvidia had agreed to pay for scarce components nor the credit support it had promised some buyers.
Nvidia disclosed $518 billion in total commitments for supply, cloud capacity and other obligations, up from $366 billion three months earlier. Supply and capacity commitments accounted for $390 billion. Of that amount, $203 billion falls due in fiscal 2028. Nvidia attributed the increase in supply commitments primarily to multiyear memory purchases; it did not identify the entire $203 billion as spending on memory alone.
Higher sales, less operating profit per week
Revenue reached $115.8 billion in the 13 weeks ended Oct. 25, up 103% from a year earlier. Data centers accounted for about 93% of sales. Management forecast $130 billion of revenue, plus or minus 3%, for the January quarter. But that quarter has 14 weeks, so the midpoint represents a smaller increase than the headline figures suggest: weekly sales would rise about 4.2%, from $8.91 billion to $9.29 billion.
Profit would move in the opposite direction. Nvidia forecast an adjusted gross margin of 71.5% at the midpoint, down from 74.8%, and operating expenses of $11 billion, up from $9.2 billion. Those figures imply adjusted operating profit of about $5.85 billion a week, down from $5.96 billion. Nvidia attributed the margin decline to the initial production ramp for its Vera Rubin platform.
A purchase commitment is a promise to buy, not an expense already incurred. Components become inventory and enter the cost of goods sold when the systems sell. By ordering years in advance, Nvidia secures supply but takes on the risk that customers cannot finance purchases on the same timetable.
Nvidia also stands behind buyers
Nvidia reported $118 billion in maximum gross exposure on guarantees. That includes $105 billion of credit support for a nine-building Ohio campus where OpenAI owes rent under 20-year leases. The guarantee takes effect in fiscal 2029. Exposure builds as the buildings come online and declines as OpenAI pays; the maximum is not a forecast loss.
Nvidia’s finance chief said some AI cloud providers and labs were growing faster than their balance sheets and long-term credit profiles could support. UBS warned that Nvidia’s purchase commitments could leave it funding customers so it can sell the supply it has ordered.
CoreWeave illustrates the distinction between orders and cash. The AI cloud provider had $132.5 billion of contracted backlog, yet its third-quarter net interest expense of $846 million exceeded its $207 million of operating profit. It recorded a $709 million net loss on $3.66 billion of revenue. Nvidia sells CoreWeave chips, owns a stake in the company and has agreed to buy $6.3 billion of its capacity through 2032.
The same buildout pays suppliers on different terms
Micron, which supplies high-bandwidth memory, said 75% of its 2027 supply was already sold. It forecast an 86.25% gross margin for the December quarter. How long that pricing power lasts is disputed: Micron’s chief executive expected tighter supply in 2027 and 2028 than in 2026, while TrendForce expected DRAM contract prices to level off in the second half of 2027 and fall in early 2028.
TSMC gets paid to manufacture wafers for competing chip designers. Broadcom’s custom chips, by contrast, depend on individual buyers’ programs: its five largest end customers accounted for about 55% of revenue, up from 40% a year earlier. Dell faces a different financing need because it assembles server racks before collecting payment. It reported a $132.3 billion AI backlog and said it checks whether buyers have access to capital, land and power.
For Nvidia investors, a nearer test was the quarterly filing due Dec. 4. After nine straight quarters of filing its Form 10-Q alongside earnings, Nvidia did not file it with the October-quarter results. Reuters reported that SEC staff were examining potential accounting issues; that report was not a finding of wrongdoing, and the agency declined to comment. UBS said management attributed the filing delay to the board’s investigation.
Nvidia reported $81 billion of receivables, and the average collection period rose from 60 days to 64. With $203 billion of supply and capacity commitments due in fiscal 2028, the timing matters: an order can demonstrate demand well before it produces the cash to pay a supplier.