The U.S. Army is offering developers 25-year ground leases at nine installations on one condition: if the grid goes down, the developer must supply power to the base within one hour and sustain it for at least 14 consecutive days. The Army will give preference to proposals that can deliver 90 days of backup power.
The Nov. 19, 2026, request for proposals is for commercial power generation. Developers may include a data center, but the Army will reject data-center-only bids. Proposals are due Jan. 18, 2027. The installations are Blue Grass Army Depot, Pine Bluff Arsenal, Tooele Army Depot, Sierra Army Depot, Fort McCoy, Fort Bragg, Fort Hood, Fort Rucker and Joint Base Lewis-McChord.
Who pays for the plant?
Rent must be at least the fair market value of the lease and must include the emergency power commitment. Federal law allows the military to accept rent in cash or in kind. The fiscal 2018 defense authorization act explicitly included utility services that prioritize resilience during commercial grid outages.
The Army will not fund construction, buy electricity or purchase computing capacity. A developer therefore needs commercial customers to cover the cost of building and running the plant, including the cost of keeping power available for the base. A long-term contract with a data center could provide that revenue. Bidders that include a data center must show how they would meet its full electricity demand within five years of signing the lease.
Compared with power projects the Army awarded at six eastern installations in September 2026, the new solicitation gives developers less time both to recover their investment and to respond to an outage. The September terms allowed leases of up to 50 years and required power within four hours. A one-hour deadline can mean paying for reserve capacity, batteries or equipment that can start quickly, even during years when the base never calls on it.
Costs beyond construction
The Army will not allow its land to serve as loan collateral, offer guarantees or generally accept financing terms that restrict its right to terminate a lease. That limits the protections a developer can offer lenders and makes the creditworthiness of a commercial customer more important.
According to law firm Holland & Knight’s reading of the lease documents, the developer must pay for the environmental review, although the Army determines its scope and makes the decision. The developer must also post a bond or letter of credit to cover decommissioning. An independent engineer sizes that obligation without credit for salvage value, and the amount is reassessed every five years.
Water is another development cost. The solicitation requires non-potable process water, no aquifer withdrawals and a water-neutral result or better. Not all the parcels have water distribution infrastructure, so developers may have to build it before a plant or data center can operate.
A solicitation, not a signed deal
On Nov. 16, 2026, Sen. Ruben Gallego filed an amendment to the defense authorization bill that would bar privately operated data centers on military installations. It had not received a vote as of Nov. 29. If enacted, it would remove the data center option, not the option to propose a commercial power plant.
Earlier Army projects illustrate the distance between developer interest and an operating plant. Neither Carlyle’s proposed lease at Fort Bliss nor CyrusOne’s at Dugway Proving Ground had been finalized as of Nov. 29. The September power projects target operation by 2030 or sooner, but still require environmental review, definitive agreements and financing. For the November solicitation, an executed lease and a signed commercial power contract would show more about the viability of the arrangement than the number of bids alone.