The U.S. Army is offering developers 25-year land leases at nine installations in exchange for rent that must include backup electricity. Its November 20, 2026, solicitation favors power plants paired with commercial data centers, but a developer can bid to build a plant alone. A data center without generation “will not be considered.”
The distinction matters for financing. The Army requires a developer to restore power to the host installation within one hour of a grid outage and sustain it for at least 14 consecutive days, preferably 90. But it makes no commitment to buy electricity or computing capacity. Developers must find their own paying customers.
What bidders would take on
Rent must be at least fair market value. The Army prefers payment in kind, with contingency power a mandatory part of that payment. It would retain title to the land, and developers could seek to renew the initial 25-year leases if justified. Projects remain subject to federal environmental review.
The Army will consider gas turbines, reciprocating engines, fuel cells, hydrogen, advanced nuclear, batteries and solar paired with generation that can run on demand. Nuclear reactors may not exceed 500 megawatts per unit; that figure is not a capacity limit for each site or for the program. Water use must be net-neutral or better.
The nine installations are Fort Bragg in North Carolina, Fort Hood in Texas, Fort Rucker in Alabama, Fort McCoy in Wisconsin, Joint Base Lewis-McChord in Washington, Blue Grass Army Depot in Kentucky, Pine Bluff Arsenal in Arkansas, Tooele Army Depot in Utah and Sierra Army Depot in California. Site tours are scheduled for November 30 through December 17, 2026. Bids under solicitation DACA27-1-27-0015900 are due January 18, 2027.
Why a commercial customer matters
Most of the installations are in states where regulated utilities dominate retail electricity sales. A developer needs to establish how its plant will connect to the grid and what price it can earn for its output. A data center on the leased property could provide a buyer willing to pay a market price for power. The solicitation offers no guarantee that such a tenant will sign.
Federal cost benchmarks illustrate the size of the financing decision. A Sargent & Lundy study for the U.S. Energy Information Administration estimated overnight construction costs, excluding financing, at $868 per kilowatt for a 1,227-megawatt combined-cycle gas plant and $8,936 per kilowatt for a 480-megawatt small modular reactor plant, both in 2023 dollars. Applying those rates to 500 megawatts gives roughly $434 million for gas and $4.5 billion for nuclear. Those are comparisons, not cost estimates for an Army project.
Five sites have disclosed about 2,723 acres in total, but acreage alone says little about the cost of serving a tenant. At Blue Grass, for example, a 69-kilovolt power line crosses the parcel, but there are no water distribution lines. At Tooele, groundwater contamination prevents new wells on two of the three parcels.
Earlier selections are not signed leases
The new solicitation changes the emphasis of the Army’s earlier rounds. In March 2026, it announced conditional selections for hyperscale data centers: Carlyle at Fort Bliss in Texas and CyrusOne at Dugway Proving Ground in Utah. Neither lease had been finalized as of late November, according to Military.com. A September round, by contrast, produced conditional selections for power generation at six installations without calling for data centers.
Ameresco, selected in that round for Aberdeen Proving Ground and Picatinny Arsenal, said the projects were not in its reported backlog as of June 30, 2026. It cautioned that the announcement was “not necessarily indicative of the timing or amount of revenue that may be recognized.”
There is also an unresolved legislative question for developers considering a data center. On November 16, 2026, Sen. Ruben Gallego filed an amendment to the defense authorization bill that would bar new privately operated data centers on military installations except those run by or for the Defense Department. It had not come to a vote as of late November. Under the solicitation as issued, a developer can leave out the data center, but it still needs customers whose payments can support the cost of the plant.